Agilent Technologies, Ipswich
Research
and Development Facility
Client: Agilent Technologies
Contract Details:
Value: £15m
Construction Period: 11 months
Procurement Route: Two Stage tender with separate contract
for infrastructure
Castons Involvement: Project Manager, Construction Cost Manager/Quantity
Surveyor
The project involved the Construction of a
new research and development facility on the site of the client's
existing estate. The project had a fast track programme with a start
on the construction works being required within 3 months of Castons
being appointed as the Project Manager for the scheme. The project
brief was developed in close liaison with the clients Facilities
Manager and the intended users, aligning their requirements with
the Client's defined business case.
Castons, alongside the client, created the
project team selecting suitable consultants and defining the lines
of communication and team structure. In order to maximise the collaboration
of all partners a project team website was developed to provide
a focal point for the teams communications.
With Castons leading the team major orders
for items with long delivery periods were negotiated and pre-ordered
and the main contractor for the project was then selected. Castons
were also involved with liasing with the client's legal consultants
to ensure that the legal framework of the project was correctly
developed.
The final building that was constructed comprised
of a 3-storey structure. Each storey was over 8m high in order to
incorporate the extensive services that were required. Due to the
sensitive nature of the work involved in the buildings the operational
areas required an anti vibration construction. The plant areas were
constructed on an isolated gantry to the main frame in order to
eliminate vibration transfer to the operational floor areas.
|